Hello Experts!!
I have a query..
I have a Finish Good Item A which is made Raw Material B using 1 Qty.
I have given the values in Work Centre
At work center | Values |
Direct unit Cost | 12 |
Overhead Rate | 10 |
Unit Cost Calculation | Time |
Unit Of Measure Code | Minute |
Queue Time | 1 |
Queue Time Unit of Measure | Minute |
At Routing | Time unit of measure | |
Setup Time | 2 | Minute |
Run Time | 20 | Minute |
wait Time | 2 | Minute |
Move Time | 1 | Minute |
Concurrent Capacity | 1 | |
Unit Cost | 0 |
LDC of Raw Material 1.09
Then i made a production Order for FG Item Qty 12 as i Update the unit Cost it Gives Me cost 441.09
Now i am Confuse in system Calculation how It is calculating.
according to me 25*12=300
material Cost 12*1.09=13.08
Total is 313.08
Can any one tell me how 441.09 is coming?
Thanks & Regards
Manish