Unit Cost Updation at Production Order. 5SP1 version

 

Hello Experts!!

I have a query..

I have a Finish Good Item A which is made Raw Material B using 1 Qty.

I have given the values in Work Centre

 

At work centerValues
Direct unit Cost12
Overhead Rate10
Unit Cost CalculationTime
Unit Of Measure CodeMinute
Queue Time1
Queue Time Unit of MeasureMinute

 

 

At RoutingTime unit of measure
Setup Time2Minute
Run Time20Minute
wait Time2Minute
Move Time1Minute
Concurrent Capacity1
Unit Cost0

LDC of Raw Material    1.09

 

Then i made a production Order for FG Item Qty 12 as i Update the unit Cost it Gives Me cost  441.09

Now i am Confuse in system Calculation how It is calculating.

according to me 25*12=300

material Cost 12*1.09=13.08

Total is  313.08

Can any one tell me how 441.09 is coming?

Thanks & Regards

Manish